Tony Prince and his team are working on the Recreation and Wellness Intranet Project. They have been asked to refine the existing cost estimate for the project so they can evaluate supplier bids and have a solid cost baseline for evaluating project performance. Recall that your schedule and cost goals are to complete the project in 6 months for under $200,000.

Use the Cost Estimate template and Cost Baseline template to assist with this assignment.

Tasks

  1. Project management
  2. Requirements definition
  3. Website design

        a. Registration for recreational programs

        b. Registration for classes and programs

        c. Tracking system

        d. Incentive system

  1. Website development

        a. Registration for recreational programs

        b. Registration for classes and programs

        c. Tracking system

        d. Incentive system

  1. Testing
  2. Training, rollout, and support

a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

b. Use the CPI to calculate the estimate at completion      (EAC) for this project. Is the project performing better or worse than      planned?

c. Use the SPI to estimate how long it will take to finish      this project.

After completing your charts, write a 150-word follow-up in which you complete the following:

APA format!